CS615 GDB solution
Saturday, January 22, 2011 Posted In CS and IT Edit ThisThe primary results of the Monitoring and Controlling processes are the project performance reports and implementing project changes. The focus for project management is the analysis of project performance to determine whether a change is needed in the plan for the remaining project activities. In my experience, almost every project will require a change to the plan at some point in time. Traditional projects are the most stable projects because the requirements and the activities are clear and well understood. Adaptive and Extreme projects are the least stable. They require very close control and will require numerous changes - if for no other reason the project manager will need to refine the activities of later phases based upon the results of early activities.
Tools and techniques that are used by project managers to conduct the Monitoring and Controlling of a project fall into one of four general categories. The first is the collection of project performance information. Techniques supporting this category are Pulse Meetings, Variance Reports, and Program Reviews. The second category is the analysis of the project performance to determine whether a project change is needed. Techniques that are used in this category are Project Forecasting and Problem Solving. The third category is reporting on project performance. Techniques that support this activity include the use of a Project Management Information System, Management Reviews, and Dashboards. The final category is the management of project change. The technique I commonly use in this category is the maintenance of a Change Management Log. There are two areas of project management tools and techniques that closely support the Monitoring and Controlling process but are also used more broadly throughout the project lifecycle. These are important enough to justify their own page.
Program Reviews are meetings with the project team members that review the current status of the project as compared to the original project plan. These are most often used on Full-scale and Complex projects. Unlike the Pulse Meetings which focus on day-to-day activities, the Program Reviews focus on the big picture and emphasize the integration between activities and between sub-projects encompassed within the project. The question being asked is whether the project activities and the sub-projects are likely to interfere with each other. In addition, when I have a supplier who is a major contributor on the project and is performing customized work on this project, I will conduct Program Reviews with the supplier for their portion of the project. Program Reviews are sometimes combined with Management Reviews. The danger with this approach is that key stakeholders and managers may intimidate some project team members from providing a frank and honest appraisal of status.