Islamic Books in Urdu ! Beauty Tips in Urdu ! Online VU Lectures ! Unique Wallpapers ! Cooking Recipes - Urdu ! Women Kahani Ghar ! Health Tips in Urdu ! Showbiz Hidden Stories ! News Updates Online ! Bachon Ki Duniya ! Virtual University Study ! Prep to PhD Study Help ! Girls Women Block ! AIOU Study Block ! News & Politics Block ! Mix Plate Block - Others
Wapda is controlling all the energy ventures in Pakistan. What type of market competition it is? Elaborate your answer with some relative example.
Wapda is a public sector and it is a monoply competitive...
where is one seller and many buyers.
no one can enter in the market without its permission
SOLUTION:
The Work Breakdown Structure (WBS) is the basis for scheduling techniques such as the Arrow Diagramming Method and the Precedence Diagramming Method. At low levels of the Work Breakdown Structure (WBS), the interdependencies between activities can become so complex that meaningful networks cannot be constructed. To cater to the above-mentioned problems, one solution is to create "hammock" activities, which encompass several activities where exact cost identification cannot or may not be accurately determined. Some projects identify a "hammock" activity called management support (or project office), which includes overall project management, data items, management reserve, and possibly procurement. The advantage of this type of hammock activity is that the charge numbers are under the direct control of the project manager. In addition to this, there is a common misconception that the typical dimensions of a work package are approximately 80 hours and less than two weeks to a month. Although this may be true on small projects, this would necessitate millions of work packages on large jobs and this may be impractical, even if line managers could control work packages of this size. Cost analysis down to the fifth level is advantageous, from a cost control point of view. However, it should be noted that the cost required to prepare cost analysis data to each lower level might increase exponentially, especially if the customer requires data to be presented in a specified format that is not part of the company's standard operating procedures. The level-5 work packages are normally for in-house control only. Some companies bill customers separately for each level of cost reporting below level 3.
Breaking the work down to small work packages can provide accurate cost control if, and only if, the line managers can determine the costs at this level of detail. Line managers must be given the right to tell project managers that costs cannot be determined at the requested level of detail.
Back to home VUsolutions
Shaadi.com: Just create ur account & find ur partner or EARN money, its reall & EASY
VUsolutions Followers (Join NOW and Get Extra Benefits)
VU related Blogs
Install LATEST toolbar having lot of features - GET solutions on Desktop
toolbar powered by Conduit |